Event protocol for data understanding 
Date: 04.04.2025  
Authors: Jonathan Magin, Robin Zink

---------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------

Machine:
The experiments were carried out on an industrial Throughput Parts Cleaning Machine (TPCM) at the ETA factory.
The machine is equipped with power measurements (1 Hz) on electrical component level. The Dataset contains 1 min averaged data of sensor and control values.


Experimental series:
To induce different concept drifts for validation, we performed a series of different production tasks on the machine. 
The target schedule for all production days started with heating up at 8:00 followed by operation from 8:30-11:30 and from 12:30-16:00. 
All tasks were conducted in continuous operation mode with typical process parameters, but no parts were conveyed through the system as process results were not subject of interest. 
During the experiments, we used the following tasks and process parameters:
- Reference: Target temperature for the aqueous detergent is 50 â—¦C for both tanks. Target temperature of the drying air is 70 â—¦C. Fan speed is 870 rpm for all fans.
- Increased fan speed: All parameters stay the same as in reference except of an adjusted fan speed of 3000 rpm.
- Increased drying temperature: All parameters stay the same as in reference except of an adjusted target temperature for the drying air of 60 â—¦C.
- Increased tank temperature: All parameters stay the same as in reference except of an adjusted target temperature for the tanks of 60 â—¦C.
- Infrared drying: All parameters stay the same as in reference except of infrared drying is used instead of the electrical air heater.

-------------------------------------------------------------------------------
-------------------------------------------------------------------------------
Set Parameters for different production tasks

| Name                		| T_tank     | T_Drying | Fans  	| IR  |  
|-------------------------------|------------|----------|---------------|-----|
| V1 - Reference		| 50°C       | 70°C     | 870 for all 	| No  | 
| V2 - Increased Mechanics 	| 50°C       | 70°C     | 3000 for all 	| No  |  
| V3 - Increased T_dry    	| 50°C       | 90°C     | 870 for all 	| No  |  
| V4 - Increased T_Tank   	| 60°C       | 70°C     | 870 for all 	| No  |  
| V5 - IR Radiator        	| 50°C       | 70°C     | 870 for all 	| Yes |  

No parts during operation.

---------------------------------------------------------
Event protocol
---------------------------------------------------------

-------- 16.05.2024 ----------  
  
08:10: Machine turned on and values set to V1  
09:00: Start operation 
09:05: Troubleshooting 
09:35: Machine restarted  
09:40: Troubleshooting 
09:56: Restart
11:30: Pause  
12:20: V2 operation 
16:00: Shutdown  

------- 21.05.2024 --------

08:05: Machine on; set V2
08:45: operation  
08:55: Troubleshooting 
09:10: Operation 
11:30: Pause  
12:30: Set V3 and heating started   
12:55: Operation  
14:30: Troubleshooting  
14:45: Troubleshooting 
14:51: Operation  
16:00: Machine off 

-------  22.05.2024 --------

08:05: Machine on; set V4
09:00: start Operation
11:30: Pause
12:37: Set V5
16:00: Stop Operation


----------  23.05.2024 ------------
 
08:00: Machine on, V1 values set  
08:20: V1 operation
09:00: V2 operation  
09:11: Troubleshooting
09:20: Operation restarded 
10:00: V1 operation
10:30: V3 operation  
11:30: Pause  
12:40: V4 operation
13:15: V5 Operation additional heat as  disturbance
13:45: V5 operation 
14:35: V1 operation
15:00: set V4 heating started  
15:10: V4 start  
16:00: Machine off  

------------ 12.07.2024  ------------

08:10: Machine On V1   
08:34: Heating                                     
08:59: V1 operation                        
09:08: Troubleshooting    
09:09: Operation                                   
09:13: Troubleshooting    
09:14: Operation                                   
09:18: Troubleshooting   
09:19: Operation                                   
09:23: Troubleshooting   
09:28: Operation                                   
09:32: Troubleshooting  
09:37: Operation                                   
11:35: Pause                                   
12:30: Operation                                   
13:58: End of continuous operation                         


------------ 16.07.2024 ------------

08:12: Machine on, set V2
08:31: Operation
11:30: Pause
12:30: Operation
16:00: Machine off


------------ 18.07.2024 ------------

08:07: Machine on, set V3              
08:11: Heating started                 
08:35: Operation 
11:30: Pause
12:30: Operation    
13:20: Stopp 

---------- 23.07.2024 ----------

08:10 Machine on, set V4
11:30: Pause
12:30: Operation
17:35 Machine off